Injection mould drawing: two tool halves, cavity, gate and ejector pins
Blog

Where your $80,000 injection mold actually goes — a cost breakdown

Steel cost. Machining hours. Polish hours. Inserts. Trial shots. Where every dollar of mold tooling goes, with real shop numbers.

Wuxi, ChinaMOQ 1 partDFM review included

The headline cost categories

A $80,000 single-cavity production mold (P20 steel, 100K-shot life, SPI A2 polish on the cavity, side action for one undercut) breaks down approximately as: tool steel $5K, CNC roughing $15K, EDM finishing $14K, hand polishing $10K, side-action mechanism $9K, ejector system $6K, hot runner $12K, trial shots and tuning $9K. Total $80K. Different molds shift these numbers, but those proportions are typical.

What you can change

Hot runner adds $10-25K but eliminates runner waste and shortens cycle time — pays back above 50K shots. Multi-cavity adds 60-80% to cost for double the throughput — pays back above 100K shots per year. Hardened steel (H13) adds 30% over P20 but lasts 5× longer — pays back above 500K total shots. Polish level: SPI A1 mirror is 2× the cost of A3 satin. Most cosmetic parts are fine with A2.

Side actions and lifters add $5-15K each and pay back essentially never on cost — they exist because the geometry has undercuts. Cheapest fix is to redesign the part to avoid them.

When to skip the steel mold entirely

Aluminum bridge tooling at $12-25K gets you 5-10K shots in 2-4 weeks. For pre-launch validation, market testing, or any volume below 5K parts/year, aluminum tooling is the right answer. We see customers spend $80K on steel tooling for products that ship 3K units total — that money should have stayed in their bank.

Have a part in mind?

Send us your CAD — quote with detailed pricing and DFM feedback within 4 working hours. No forms, no signup.

From the blog

How tight is too tight? A real-world CNC tolerance guide for 2026

Specifying ±0.005 mm because "tighter is safer" can multiply your part cost by 5-10×. Here is what tolerance you actuall...

6061 vs 7075 aluminum: when paying 3× for 7075 actually pays back

7075-T6 has 80% higher yield than 6061-T6 and costs 3× more. Here is the practical decision tree we walk customers throu...

Anodize Type II or Type III? A finish guide for engineers

Type II is for color, Type III is for wear. The hard part is knowing which trade-offs you are making with each....

Upload a CAD file. Get an engineering-reviewed quote in under 24 hours.

No minimum quantity. Free DFM feedback from a senior manufacturing engineer. NDA signed before file review on request.

Working on a live project? Send the STEP file and the two or three features you are unsure about — an engineer replies with DFM notes and a price, usually within four working hours.

5-axis CNC milling drawing: Al 7075-T6 block with pockets, toolpath and dimensions

Send a CAD file. Get an engineering-reviewed quote.

No minimum quantity, free DFM feedback from a senior manufacturing engineer, and an NDA signed before file review on request.